PMC is the General Contractor for the integration of a new production well at the existing 22 MW Blundell Geothermal Power Plant. PMC is responsible for installation of new well head valves, brine separator, pumps, new service building, air compressor system, all electrical and instrumentation and a new emergency generator. Work includes all civil and structural foundations and the supply and installation of new overhead power poles, transmission line, and a new step-down transformer.